The Building Fund has covered several fully paid expenses, which are itemized below. Our goal is to replenish the fund with these amounts. Additionally, a separate breakdown is provided for contributions received back into the Building Fund since December 2024.
- Blower Motor in AC Unit of Ministry Building ~ $ 1,402.68
- AC Unit in Foyer of Sanctuary Building ~ $ 10,129.76
- Allen Heath QU-32 Sound Board ~ $ 4,294.54
- Three TVs in Sanctuary & One TV in Upstairs Nursery ~ $ 1,080.20
- Computer Parts (WiFi Switch, HDMI Switches, Misc Hardware) ~ $ 517.15
- Light Fixtures for Ministry Building ~ $ 68.46
- Tree Removal ~ $700.00
- Total Spent through Current Date ~ $ 18,192.79
- Total Received December 1, 2024 - Current Date ~ $ 13,412.30
- Total Amount Needed for Building Fund ~ $ 4,780.49
- Percentage left needed ~ 26.27%
- Information Updated: Sunday, November 9, 2025 at 9:00am
We will update the numbers on this page each week. The only big item left to purchase from the lightening damage is the heater for the baptism pool.